9/28 Got a bit off track in September with 1) paying jobs, 2) Art in the Park preparation, and 3) a closet upgrade for my wife. Would be much more impressive if I had remembered to take a before and after! | |
9/12 Opened up alcove, framed. By raising the height of the header at the top of the alcove, there will be room above the fridge for a cabinet - thus helping the "built-in" look. An unexciting detail that will be important later. | |
9/8 - Hard to photograph... temporarily supported ceiling to allow alcove to be fully opened up |
another view of the alcove with old protruding framing removed |
9/7 - Cleaned up and removed about 15 bags of trash / debris... |
...that were left from the door installation |
Also continued to salvage cherry for other projects |
|
Fridge alcove framing started |
Interested witnesses |